The California Department of Transportation reports the following update for the I-10 “Tune Up” Pavement Rehabilitation Project, a major rehabilitation project on nearly 20 miles of I-10 from Beaumont to SR-111.
Daytime Work: Monday ā Friday from 6 a.m. to 6 p.m.
NO PLANNED LANE CLOSURES
- Westbound crews continue electrical work, demolition, paving and excavation from 8th Street in Banning to Main Street in Cabazon.
- Eastbound crews continue work on joint sealing on the outside lanes and shoulders from Main Street in Cabazon to SR-111.
- Eastbound and Westbound crews continue electrical work throughout the project area.
Nighttime Work: Mondayā Friday from 7 p.m. to 6:30 a.m.
NIGHTTIME ALTERNATING LANE CLOSURES IN BOTH DIRECTIONS ā Expect delays, Allow additional time for travel
- Westbound and Eastbound crews continue paving work throughout the entire project from Beaumont to SR-111.
LONG-TERM RAMP CLOSURE: Due to high winds and poor field conditions the anticipated ramp openings have been DELAYED.
- Opening anticipated the week of May 24th weather permitting
- Eastbound Haugen-Lehman Way on-ramp remains closed for improvements.
- DETOUR: to travel east, please use Eastbound Main Street on-ramp via Railroad Avenue to access EB I-10.
- ALTERNATE DETOUR: to travel east, enter Westbound I-10 Haugen-Lehman Way on-ramp, exit Main Street off-ramp, re-enter Eastbound I-10 on-ramp to continue east.
- Anticipated from Monday, May 24 through late-June weather permitting
- Westbound Truck Scales will be closed for improvements.
10 DAY RAMP CLOSURES: Due to high winds and poor field conditions the anticipated ramp openings have been DELAYED.
- Opening anticipated the week of May 24th weather permitting
- Eastbound Haugen-Lehmann Way off-ramp remains closed for improvements.
- DETOUR: please exit EB Whitewater off-ramp, re-enter WB I-10 on-ramp, exit WB Haugen-Lehmann Way off-ramp.
- Opening anticipated the week of May 24th weather permitting
- Westbound Morongo Trail on-ramp remains closed for improvements.
- DETOUR: to travel west, please use WB Malki Road or Westbound Main Street on-ramps to access WB I-10.
- Opening anticipated the week of May 24th weather permitting
- Westbound Malki Road off-ramp remains closed for improvements.
- DETOUR: please exit Westbound Morongo Trail off-ramp.
- Anticipated from the week of May 31st weather permitting
- Westbound Malki Road on-ramp will be closed for improvements.
- DETOUR: to travel west, please use Westbound Morongo Trail or Westbound Main Street on-ramps to access the Westbound I-10.
INTERMITTENT CONNECTOR RAMP CLOSURE: EB connector on-ramp to SR-111 may intermittently be closed for roadwork, please use Whitewater/Tipton Road or Indian Canyon Road to access SR-111.
ADVISORY
- Please REDUCE YOUR SPEED when driving throughout the project area.
- Westbound CROSSOVER LANE from Main Street in Cabazon to 8th Street in Banning is AVAILABLE tomotorists, NO trucks towing trailers, buses, or RVās permitted.
- All ramps and lanes in the project area are subject to brief intermittent closures, for staging and other construction improvements.
- ALL WORK is WEATHER and field condition DEPENDENT.
- Dates and times are subject to change.
On the road? Why not take us with you. All our websites are mobile-friendly. Visit our growing family of exit guides: I-4 Exit Guide, I-5 Exit Guide, I-10 Exit Guide, I-75 Exit Guide, and I-95 Exit Guide. Detailed exit service listingsā¦ discount lodging, camping, food, gas and more for every exit along the way!